Different activity and Timelines for various activities for Rule 38 transfer as per order dt 03.02.2023

Different activity and Timelines for various activities for Rule 38 transfer as per order dt 03.02.2023

Sl No

Activity

Timelines

(a)

Capturing of vacancy

01st – 05th of March / June / September / December by Divisions

(b)

Forwarding / acceptance of request by controlling unit

Real - time basis. Requests received till last day of Feb / May / Aug / Nov should be verified before 5th March / June / September / December

(c)

Provisional allotment of Intra – Circle transfer

11th of March / June / September / December

(d)

Acceptance / Refusal of provisional allotment of Intra – Circle transfer by employee

12th – 14th of March / June / September / December

(e)

Release of approved list of Intra – Circle transfer

15th of March / June / September / December

(f)

Relieving of employees approved for Intra – Circle transfer

Latest by 15th April / July /  October / January, except in case of pending disciplinary proceeding or on own request

(g)

Provisional allotment of Inter – Circle transfer

17th of March / June / Sep / Dec

(h)

Acceptance / Refusal of provisional allotment of Inter – Circle transfer by employee

18th – 20th of March / June / Sep / Dec

(i)

Release of approved list of Inter – Circle transfer

21st of March / June / Sep / Dec

(j)

Relieving of employees approved for Inter – Circle transfer

Latest by 21st April / July /  October / January, except in case of pending disciplinary proceeding or on own request

 We are now at the highlighted stage (f) above...